Old Lynchburg Road Safety, Sidewalks and Drainage Project Update


From Charlottesville City Engineer Tony Edwards:

Week Feb 4 to Feb 8

Monday thru Friday moving to east side of OLR, on Middleton Lane, to install more storm pipe.

This will include excavation and placement of three structures and the pipe in between those structures.

One lane of traffic will be maintained during construction.

.

Week Feb 11 to Feb 15

Road closure of old Lynchburg per approved MOT plan

Installation of structure 103-11 and structure 103-1

Clearing crew uses availability of road closer to do remaining clearing.

Ms. Matos tree to be removed Monday per my conversation with her

End of week 2 Middleton and Old Lynchburg Rd. will be reopened