Old Lynchburg Road Safety, Sidewalks and Drainage Update

Old Lynchburg Road Project is proceeding on schedule with approximately 23% of the work complete. Here is the proposed work schedule  this week, weather permitting.

April 8 ,2013 thru April 13,2013
Monday- surveyors providing layout for retaining wall work. Ensuring clear access to FSBC. Coordinating remobilization of clearing contractor.

Tuesday – sections of water services being replaced.


Wednesday- sections of water services being replaced. Also in the middle of the week our milling/ paving operations will be onsite to mill and patch all utility crossing / curb line gaps.


Thursday- the storm pipe work will continue. The clearing company and wall contractor may also be on site at various times this week.


Friday- the storm pipe work will continue.


Traffic will be controlled by flagmen and usually limited to one lane. There will be short periods of time that both lanes will be closed and traffic will be redirected to the alternate routes.  

We thank you all for sharing this anticipated work schedule with the rest of the neighborhood.


Tony Edwards
City Engineer, CFM