Old Lynchburg Road Safety, Sidewalks and Drainage Project Update

From Charlottesville City Engineer Tony Edwards:

Hello everyone,We have made a lot of good progress since the last schedule update. If the weather will allow it the plans are to have a lot more activity within the project limits. I appreciate the neighborhoods support and patience with the interruptions to normal use of the area. As indicated by the schedule below, we are hopeful that more of the areas can be dressed up soon. May 20, 2013 thru May 24, 2013
Storm structures from #120 OLR to J.P.A will be installed which will complete main storm run.

Concrete crews will be working on curbs and aprons at 241 OLR thru 236 OLR, then jumping over to 223 OLR and continue up OLR, as weather and time allows. These addresses will be notified day prior.

The grading crew will be working in the bio-retention pond area and will start trucking in fill material Tuesday.

* The railing contractor will be scheduled to install railings in designated area behind the sidewalk.

May 27 thru May 31
Utility crew will complete the water services this week and double check for completeness.

Concrete crews will continue at curbs / aprons at 219 OLR heading up OLR

Strom water management pond will be rough graded then lining crew will move in to install liner and bio- mix.

Light company will bore under OLR to install crosswalk controls


* all work controlled by weather* expect road closer every day to all thru traffic. Local traffic will have controlled access.


Tony EdwardsCity Engineer, CFM