Audio Player

Wednesday, June 26, 2013

Proposed By-Right Development for Eton Road

At the June FSNA meeting, property owner Alex Hancock presented a site plan for a by-right development of his property.


The red area in the map above represents the area of proposed development.

Proposed Site Plan (Larger PDF version)

Thursday, June 13, 2013

Dangerous Blind Spot on Jefferson Park Avenue?

A Robertson Avenue neighbor raised a concern at the June Fry's Spring Neighborhood Association meeting regarding the blind spot created by the new "Welcome to Fry's Spring" sign when turning left onto Robertson Avenue from Jefferson Park Avenue. He shot a video to illustrate his concern. The map below shows the route the video depicts.



View Blind Spot in a larger map


Sunday, June 9, 2013

Old Lynchburg Road Safety, Sidewalks and Drainage Update

Hello everyone,
I have copied Finley’s schedule for the month of June. Once the weather clears we should be seeing a great deal of activity and production. They are attempting to complete the project ahead of schedule and your continued cooperative spirit and willingness to adjust as needed really is appreciated. Finley will have a crew on site tomorrow, 6/8/2013, to address the potholes that have been enlarged due to the bad weather and high volume of traffic.  We encourage anyone who can avoid driving on Old Lynchburg Road to do so for the next 2 to 3 weeks, so that this work can be completed early without too many interruptions.

THIS SCHEDULE IS TO HELP YOU AND HOMEOWNERS UNDERSTAND WHAT WE AT FINLEY ARE TRYING TO ACCOMPLISH WHITHIN THE NEXT  WEEKS AND HOPEFULLY THE CLOSE OF THE PROJECT. (WEATHER PERMITTING, ROCK PERMITTING OR HOMEOWNER WANTS OR NEEDS)

AS YOU KNOW WEATHER WAS A FACTOR YESTERDAY WITH THE RAIN AND MY CREWS GOT A HALF DAY IN AND SEEMS TODAY WILL BE A WASH

JUNE 10,2013 THRU JUNE 14, 2013

MONDAY – PIPE CREW - WILL BE WORKING SIDE BY SIDE WITH CITY TO REMOVE WATER SERVICE AT TWO LOCATIONS AND RE-TAPING SERVICE TO
                        TO THE 12”MAIN IN WHICH WE WILL TERMINATE THE 2” MAIN LINE
                        CONCRETE CREW  -WILL BE CONTINUING UP STREET AS THEY HAVE WITH CURB/APRONS NOTIFING DAY BEFORE OF WORK THAT WILL
                        BE COMING THEIR WAY –( HOMEOWNERS HAVE BEEN POSITIVE )
                        GRADE CREW – ARCHIE WILL BE HANDLING THIS WITH HIS CREW THAT’S PROVIDED WHICH IS DEMO OF DRIVEWAY PAVEMENT /FILL
                        GRADE FOR STONE THEN PLACE STONE. THIS CREW IS ALSO BACKFILLING SIDEWALKS /SEED AND STRAWING

TUESDAY – CONCRETE CREWS  (REFER TO MONDAY)
                        GRADING CREWS   (REFER TO MONDAY)
WEDNESDAY –CONCRETE CREWS (REFER TO MONDAY)
                              GRADING CREWS (REFER TO MONDAY)

THURSDAY- CONCRETE CREWS (REFER TO MONDAY)
                         GRADING CREW (REFER TO MONDAY
GRADING CREW X2 –THIS CREW IS JERRY WHO IS MOVING BACK IN TO COMPLETE THE ROUGH GRADE AT POND. THIS WORK INTELS BRINGING IN LAST 100YDS OF MATERIAL , FINE DRESSING,AND INSTALLING THE 2 RIPRAP CHANNELS TAT LEAD IN  AND OUT OF POND ALSO PLACING APPROX 28 TONS OF RIP RAP AT AREA NEAR HOUSE WHERE EXSISING STORM RUN STARTS.

FRIDAY – CONCRETE CREW –(REFER TO MONDAY)
                   GRADING CREW –(REFER TO MONDAY)
                   GRADING CREW X2 – (REFER TO THURSDAY INSTALL GABION BASKETS IN POND

JUNE 17,013 THRU JUNE 21 ,2013

MONDAY – PIPE CREW WORKING ALONG WITH CITY WILL REMOVE WATERSERVICE AT 2 LOCATIONS   FROM EXSISTING MAIN AND RE TAP ONTO  12” MAIN. THIS IS SCHEDULED FOR 10AMAND HOMEOWNERS WILL BE NOTIFIED DAY BEFORE AND WHEN WATER IS SHUTOFF.  CONCRETE CREWS – CONTINUE CURBS AND APRONS BOTH SIDES OF STREET IN WHICH HOMEOWNERS WILL BE NOTIFIED DAY BEFORE

TUESDAY – PIPE CREW (REFER TO MONDAY BUT AT DIFFERENT LOCATION ALSO SCHEDULED FOR 10 AM)
                       CONCRETE CREW (REFER TO MONDAY)
                       GRADING CREW – CONTINUE BACKFILL SIDEWAKS AND CURBS PREPPING DRIVEWAYS
                      RAILING CONTRACTOR – INSTALL RAILINGS AT 2 LOCATIONS

WEDNESDAY –PIPE CREW (REFER TO MONDAY BUT AT FINAL LOCATION SAME TIME 10AM FOR TAP WITH CITY
                             GRADING CREW ( REFER TO TUESDAY)
                             CONCRETE CREW –(REFER TO MONDAY)
                           
THURSDAY- PIPE CREW - HAS A REPAIR THAT NEEDS DONE WHICH WE NOTICED THAT HAPPENED EARLY IN THE PROJECT ALONG WITH FINAL PUNCH
                        ITEMS WILL BE ADDRESSED (PARGE, ADJUSTMENTS ,VISUAL INSPECTIONS
                        CONCRETE CREW – (REFER TO MONDAY)

FRIDAY – PIPE CREW- CONTINUE FINAL NEEDS
                   CONCRETE CREW- CONTINUE CURBS /APRONS

IN THIS WEEK WE WILL BE HAVING A CREW MOVE IN TO EXCAVATE UTILIY CROSSINGS AND ALONG CURBS FOR PLACEMENT OF ASPHALT I
WILL VERIFY THESE DAYS . (NO MORE POTHOLES) THE FOLLOWING WEEK LOOK FOR ASPHALT SPOT MILLING ALONG WITH ASPHALT BUILD-UP.
WE ARE HOPING TO DO FINAL PAVING OF DRIVEWAYS AND ROADWAY POSSIBLY LAST WEEK OF JUNE OR FIRST WEEK OF JULY DEPENDING IF WE HAVE ANY ISSUES WITH WEATHER.

Thank you all again and I hope all of you have a good weekend!


Tony Edwards
City Engineer, CFM

Saturday, June 8, 2013

Cleveland (and JPA) Street Clean Up a Success!

Thanks to those members of the Fry's Spring neighborhood who came out this morning to help make our neighborhood a little bit cleaner. Despite gloomy skies the rain held off until we had not only picked up trash from both sides of Cleveland Avenue (from Cherry Avenue to Jefferson Park Avenue), but had also cleaned along JPA all the way to the new bridge!


IMGP1588

Wednesday, June 5, 2013

Let's Clean Up Our Neighborhood! (or at least a small part of it)

This Saturday, the 8th of June, at 9:00 am, interested neighbors can meet in front of the Cherry Avenue Christian Church for a street clean-up of Cleveland Avenue from the intersection with Cherry Avenue up to Jefferson Park Avenue. If there is time will will continue down Jefferson Park Avenue. We will be done in an hour. Children are welcome and please bring gloves if you have them.

Rain will cancel this event.

For more information please contact phedlund @ gmail.com.


View Cleveland Avenue Cleanup in a larger map