Hello everyone,
I have copied Finley’s schedule for the month of June. Once the weather clears we should be seeing a great deal of activity and production. They are attempting to complete the project ahead of schedule and your continued cooperative spirit and willingness to adjust as needed really is appreciated. Finley will have a crew on site tomorrow, 6/8/2013, to address the potholes that have been enlarged due to the bad weather and high volume of traffic. We encourage anyone who can avoid driving on Old Lynchburg Road to do so for the next 2 to 3 weeks, so that this work can be completed early without too many interruptions.
THIS SCHEDULE IS TO HELP YOU AND HOMEOWNERS UNDERSTAND WHAT WE AT FINLEY ARE TRYING TO ACCOMPLISH WHITHIN THE NEXT WEEKS AND HOPEFULLY THE CLOSE OF THE PROJECT. (WEATHER PERMITTING, ROCK PERMITTING OR HOMEOWNER WANTS OR NEEDS)
AS YOU KNOW WEATHER WAS A FACTOR YESTERDAY WITH THE RAIN AND MY CREWS GOT A HALF DAY IN AND SEEMS TODAY WILL BE A WASH
JUNE 10,2013 THRU JUNE 14, 2013
MONDAY – PIPE CREW - WILL BE WORKING SIDE BY SIDE WITH CITY TO REMOVE WATER SERVICE AT TWO LOCATIONS AND RE-TAPING SERVICE TO
TO THE 12”MAIN IN WHICH WE WILL TERMINATE THE 2” MAIN LINE
CONCRETE CREW -WILL BE CONTINUING UP STREET AS THEY HAVE WITH CURB/APRONS NOTIFING DAY BEFORE OF WORK THAT WILL
BE COMING THEIR WAY –( HOMEOWNERS HAVE BEEN POSITIVE )
GRADE CREW – ARCHIE WILL BE HANDLING THIS WITH HIS CREW THAT’S PROVIDED WHICH IS DEMO OF DRIVEWAY PAVEMENT /FILL
GRADE FOR STONE THEN PLACE STONE. THIS CREW IS ALSO BACKFILLING SIDEWALKS /SEED AND STRAWING
TUESDAY – CONCRETE CREWS (REFER TO MONDAY)
GRADING CREWS (REFER TO MONDAY)
WEDNESDAY –CONCRETE CREWS (REFER TO MONDAY)
GRADING CREWS (REFER TO MONDAY)
THURSDAY- CONCRETE CREWS (REFER TO MONDAY)
GRADING CREW (REFER TO MONDAY
GRADING CREW X2 –THIS CREW IS JERRY WHO IS MOVING BACK IN TO COMPLETE THE ROUGH GRADE AT POND. THIS WORK INTELS BRINGING IN LAST 100YDS OF MATERIAL , FINE DRESSING,AND INSTALLING THE 2 RIPRAP CHANNELS TAT LEAD IN AND OUT OF POND ALSO PLACING APPROX 28 TONS OF RIP RAP AT AREA NEAR HOUSE WHERE EXSISING STORM RUN STARTS.
FRIDAY – CONCRETE CREW –(REFER TO MONDAY)
GRADING CREW –(REFER TO MONDAY)
GRADING CREW X2 – (REFER TO THURSDAY INSTALL GABION BASKETS IN POND
JUNE 17,013 THRU JUNE 21 ,2013
MONDAY – PIPE CREW WORKING ALONG WITH CITY WILL REMOVE WATERSERVICE AT 2 LOCATIONS FROM EXSISTING MAIN AND RE TAP ONTO 12” MAIN. THIS IS SCHEDULED FOR 10AMAND HOMEOWNERS WILL BE NOTIFIED DAY BEFORE AND WHEN WATER IS SHUTOFF. CONCRETE CREWS – CONTINUE CURBS AND APRONS BOTH SIDES OF STREET IN WHICH HOMEOWNERS WILL BE NOTIFIED DAY BEFORE
TUESDAY – PIPE CREW (REFER TO MONDAY BUT AT DIFFERENT LOCATION ALSO SCHEDULED FOR 10 AM)
CONCRETE CREW (REFER TO MONDAY)
GRADING CREW – CONTINUE BACKFILL SIDEWAKS AND CURBS PREPPING DRIVEWAYS
RAILING CONTRACTOR – INSTALL RAILINGS AT 2 LOCATIONS
WEDNESDAY –PIPE CREW (REFER TO MONDAY BUT AT FINAL LOCATION SAME TIME 10AM FOR TAP WITH CITY
GRADING CREW ( REFER TO TUESDAY)
CONCRETE CREW –(REFER TO MONDAY)
THURSDAY- PIPE CREW - HAS A REPAIR THAT NEEDS DONE WHICH WE NOTICED THAT HAPPENED EARLY IN THE PROJECT ALONG WITH FINAL PUNCH
ITEMS WILL BE ADDRESSED (PARGE, ADJUSTMENTS ,VISUAL INSPECTIONS
CONCRETE CREW – (REFER TO MONDAY)
FRIDAY – PIPE CREW- CONTINUE FINAL NEEDS
CONCRETE CREW- CONTINUE CURBS /APRONS
IN THIS WEEK WE WILL BE HAVING A CREW MOVE IN TO EXCAVATE UTILIY CROSSINGS AND ALONG CURBS FOR PLACEMENT OF ASPHALT I
WILL VERIFY THESE DAYS . (NO MORE POTHOLES) THE FOLLOWING WEEK LOOK FOR ASPHALT SPOT MILLING ALONG WITH ASPHALT BUILD-UP.
WE ARE HOPING TO DO FINAL PAVING OF DRIVEWAYS AND ROADWAY POSSIBLY LAST WEEK OF JUNE OR FIRST WEEK OF JULY DEPENDING IF WE HAVE ANY ISSUES WITH WEATHER.
Thank you all again and I hope all of you have a good weekend!
Tony Edwards
City Engineer, CFM
No comments:
Post a Comment