In looking ahead towards an early finish to the OLR improvements.
July 18th - July 23rd.
We will see the completion of paving driveways, backfilling grading seeding and mulching behind the curbs and sidewalks, saw cutting the areas where full depth patching is required, milling and placing base material in Middleton, installing bio-filter materials in the pond, landscaping.
Tony Edwards
City Engineer, CFM