Fontaine/Maury/JPA Water Line Replacement Update
Here is the schedule update for the Fontaine Waterline work. There have been some technical issues to resolve that have resulted in a slight delay to the work, but we are just about ready start.
Phase 1: (JPA Bridge/Maury)
Phase 2: (Fontaine from Westerly to Appletree)
We certainly appreciate everyone's patience and cooperation as we work to complete this difficult project as quickly as possible. I will continue to send updates to this distribution list as the project continues. Please let me know if you have been added to this email list by mistake or know of someone that should be added.
Please let me know if you have any questions.
Thanks
Trip Stakem
Utilities Engineer
City of Charlottesville
970-3908
View Fontaine Water Line Replacement in a larger map
Phase 1: (JPA Bridge/Maury)
- 6/25/2012: The contractor will set up the traffic control for the night work to take place near the JPA bridge project.
- 6/26/2012: Beginning at 9 pm, the night work portion will begin adjacent to the JPA bridge project site. The night work will last approximately 2-3 weeks. During the night work, traffic on Fontaine will be detoured around Mimosa to Stadium Road and back down Shamrock to JPA, as needed. When the detour is active, local streets will remain accessible, but the intersection of JPA/Fontaine/Maury will be closed to through traffic. The intersection will be reopened by 6 am the following morning.
Phase 2: (Fontaine from Westerly to Appletree)
- 6/21/2012: The contractor will put up "NO PARKING" signs on Westerly near Fontaine and on Fontaine between Westerly and Summit. The parking restrictions will not begin until 6/25/2012 and will continue for the duration of the project, as needed.
- 6/25/2012: Work will begin on Phase 2. The contractor will begin digging test holes. Work in this area will be during the day from 9 am to 7 pm.
We certainly appreciate everyone's patience and cooperation as we work to complete this difficult project as quickly as possible. I will continue to send updates to this distribution list as the project continues. Please let me know if you have been added to this email list by mistake or know of someone that should be added.
Please let me know if you have any questions.
Thanks
Trip Stakem
Utilities Engineer
City of Charlottesville
970-3908
View Fontaine Water Line Replacement in a larger map
Wednesday, June 20, 2012
Thursday, June 14, 2012
No Trolley Service at JPA/Maury Starting June 18th
On Monday, June 18, Charlottesville Area Transit (CAT) will temporarily detour the Free Trolley due to construction work at the intersection of Jefferson Park Avenue (JPA) and Maury Avenue.
During the detour, the Free Trolley will not travel on JPA between Shamrock Road and Maury Avenue, or on Maury Avenue between JPA and Stadium Road. The CAT stops in those areas will not be served.
Instead, the Trolley will travel from JPA to Shamrock Road to Stadium Road, resuming regular route service with the stop on Alderman Road opposite the Gooch Houses.
This detour will begin on Monday, June 18 and last until further notice. CAT apologizes for any inconvenience to its customers.