Here is the Old Lynchburg Road Sidewalk Safety and Drainage Project update for 5/6/14.
 
The task order bids were received and reviewed. Vess Excavating will be performing the work.
This work is being scheduled to begin on Thursday 5/8, near the intersection of OLR and Middleton Lane.
The work will  proceed from there up Old Lynchburg Road.
It is expected that the work will be substantially completed within 21 days.
Traffic controls will be in place and traffic will limited to one lane during day time work hours.
Snow’s Nursery has begun the new tree work along the corridor.
The top soil, seeding and mulching items are to  soon follow.
 