Here is the Old Lynchburg Road Sidewalk Safety and Drainage Project update for 5/ 13/14.
Vess Excavating will start their work on 5/14/14 with saw cutting the asphalt at various location along OLR.
The drainage work is still anticipated to begin near the intersection of OLR and Middleton Lane .
The work will proceed from there up Old Lynchburg Road.
It is expected that the work will be substantially completed within 21 days.
Traffic controls will be in place and traffic will limited to one lane during day time work hours.
Neighborhood Sign location has been verified.
Snow’s Nursery has completed the new tree work along the corridor.
The top soil, seeding and mulching has begun.