2 WEEK LOOK AHEAD,
Please forward to your e-mail distribution lists for the neighborhood. I will forward to those county addresses on my list.

March 11, 2013 THRU MARCH 15, 2013

MONDAY – EXCAVATION AND INSTALLATION OF 24” RCP FROM STR# 104-1 TO 104 -4 (#227 to #223 OLR)
                        SET STR # 104-4 ( #223 OLR)
                        BACKFILL OPEN TRENCH WITH 21B
TUESDAY -  COMPLETE RCP FROM STRUCTURE 104-4 TO 104-5 (#223 OLR)
                        START 18” RCP FROM 104-4 TO 104-6 (#223 to #219 OLR)
                        BACKFILL OPEN TRENCH WITH 21 B
WEDNEDAY- DELIVERY OF STRUCTURES 104- 6 THRU 104-9
                          CONTINUE 18” RCP TOWARD 104-6 (# 219 OLR)
THURSDAY-SET STRUCTURE 104-6 (#219OLR)
                        BACKFILL TRENCH
                        SET STRUCTURE 103-4 (# 303 Middleton Lane)
FRIDAY – COMPLETE STORM RUN FROM 103-4 TO 103-3(# 303 Middleton Lane)

WEEK MARCH 18 2013 THRU MARCH 22 ,2013

MONDAY –CONCRETE CREW MOBILIZE IN
                       EXCAVATE AND PREP CURBLINE Middleton / OLR Intersection
TUESDAY- POUR CG-6 AND CG-2 CURBLINES AT VARIOUS LOCATIONS
WEDNESDAY – CONTINUE CURB AND START SIDEWALK PREP/ POUR Middleton / OLR Intersection
THURSDAY – CONTINUE CONCRETE WORK
FRIDAY – CONTINUE SIDEWALKS / APRONS/ BACKFILLING SIDEWALKS

This work will generally require at least a one travel lane to be closed during day light hours, each day. There may be brief occasions that will require a full street closure,  but in these cases traffic controls will be in place to direct local traffic into the site area or detour pass through traffic. Thanks to everyone for your cooperation and getting the message out.